Land in Kutch

Guide · Gujarat Land Revenue Code

NA conversion in Gujarat: how to get bin-kheti permission for agricultural land

To use agricultural land for industry, commerce or housing in Gujarat, the occupant needs non-agricultural (NA) permission from the District Collector under Section 65 of the Gujarat Land Revenue Code, 1879. Applications are made online on iORA, backed by the 7/12, 8A, mutation entries, a measurement sheet, a layout and any sector NOCs. Two charges can apply — a conversion tax notified by the State, and a premium if the land is new (restricted) tenure — and the use you ask for must match the development-plan zone.

Facts last reviewed on

What “NA” actually changes on a piece of land

Farmland in Gujarat is held for agriculture. Building a factory, warehouse, hotel, petrol pump or housing layout on it is a change of use, and the Gujarat Land Revenue Code says an occupant who wants that change must first get the Collector’s permission. In Gujarati this is called બિનખેતી permission — literally “non-farming” — and the order that results is the NA order, often called the NA “hukam”.

NA permission is about use, not ownership. It does not cure a title defect, it does not by itself let a non-farmer buy agricultural land, and it does not replace building permission or pollution consent. It is one link in a chain: title and tenure first, then NA, then layout and building approvals. If you have not yet bought the land, read who can buy agricultural land in Gujarat before anything else.

Section 65 and its neighbours: 65A, 65B and 67A

Several provisions of the Code work together. Knowing which one applies to your parcel tells you whether you need a full permission or only an intimation, and what you will be charged.

The Land Revenue Code provisions behind NA use
ProvisionWhat it coversPractical meaning
Section 65Agricultural land to be used for a non-agricultural purposePrior permission of the Collector is needed. This is the standard NA route.
Section 65AChange from one non-agricultural use to anotherLand already NA for, say, residential use needs fresh permission to switch to commercial or industrial.
Section 65BUse for a bona fide industrial purpose (BFIP)For land in an industrial zone of a development plan, and on the section’s conditions, prior Section 65 permission is not needed. The occupant intimates the Collector, obtains a commencement certificate and pays conversion tax.
Section 67AConversion taxA per sq m tax on land permitted (or deemed permitted) under 65, 65A or 65B. Since the 2019 amendment, rates are set by State gazette notification and vary by area class and use class.

The Gujarat Land Revenue (Amendment) Act, 2016 moved a power under Section 65B from the State Government to the Collector, so the Collector may now exempt in the cases the section describes. The industrial-intimation procedure is linked to a Revenue Department resolution whose text we have not been able to read, so confirm the current Section 65B procedure with the Collectorate before relying on it.

Inside GDA, BHADA or another development authority, the route can differ

Kutch has several development authorities, most of them constituted under the Gujarat Town Planning and Urban Development Act, 1976 (GTPUDA) after the 2001 earthquake: the Gandhidham Development Authority (GDA) for the Gandhidham–Adipur–Kandla area, the Bhuj Area Development Authority (BHADA) covering Bhuj and nearby Madhapar and Mirzapar, and area development authorities listed for Anjar, Bhachau and Rapar.

Under Section 117 of GTPUDA, where a development authority grants development permission under Section 29(2) of that Act, a separate Section 65 NA permission is not required. In practice that means a parcel inside a development-plan area may go through the authority’s development-permission process rather than a stand-alone NA file. Outside these areas — which covers most of rural Kutch, including large parts of Mundra, Abdasa, Lakhpat and Rapar talukas — NA and layout go through the Collector and taluka-level offices.

Check the authority’s jurisdiction for your survey number

We have not verified the current development-plan limits or revision status of each Kutch authority. Before you plan the route, confirm in writing whether your survey number falls inside GDA, BHADA, AADA or another authority’s sanctioned plan area, and in which zone.

The iORA application from start to NA order

Gujarat moved NA applications online through iORA (online since about December 2018). The iORA portal lists separate services for NA permission, combined NA permission with premium, permission to pay premium, the bona fide industrial purpose certificate, land purchase permission, the khedut (farmer) verification certificate, land measurement, mutation and digitally signed 7/12 extracts. A typical file moves like this:

  1. 1

    Confirm title and tenure

    Pull the latest 7/12, 8A and every Village Form 6 entry on AnyROR. Check whether the land is old tenure or new tenure — new tenure changes the whole file (see navi sharat vs juni sharat).

  2. 2

    Get the land measured if needed

    Apply for DILR measurement so the area and boundaries in your application match the ground. Mismatches between the 7/12 area and the measurement sheet are a common source of queries.

  3. 3

    Prepare a layout or site plan

    The plan must suit the zone and the intended use, and be approved by the competent authority where one is required (development authority, Town Planning or Panchayat).

  4. 4

    Apply on iORA

    Choose the correct service (plain NA, or NA combined with premium for new-tenure land), fill the application and upload all documents. Keep the acknowledgement — statutory timelines run from it.

  5. 5

    Departmental reports and NOCs

    The file is routed for inputs: DILR, Mamlatdar or Talati, Town Planning, the District Panchayat for rural roads, and sector departments where relevant.

  6. 6

    Site inspection

    Officials inspect the land, its access and its surroundings against what the application claims.

  7. 7

    Assessment and payment

    Conversion tax, and premium if applicable, are assessed. Payment is made by challan through Cyber Treasury.

  8. 8

    NA order and mutation

    The Collector issues the NA order. A mutation entry then updates the 7/12 to show NA use, and the land is usually moved to the city survey / property-card system where that applies.

Documents the Collectorate expects with an NA file

Typical NA application documents and where they come from
DocumentWhere you get itWhy it matters
Latest 7/12 and 8A extracts (digitally signed)iORA / AnyRORShows occupant, area, tenure and other rights on the date of application.
Village Form 6 (hakk patrak) entriesAnyROR, taluka e-Dhara centreTraces how the applicant acquired the land.
Title clearance / search reportYour advocateIndependent opinion that the title chain is clean.
DILR measurement sheet or mapDistrict Inspector of Land RecordsFixes area and boundaries.
Site or layout planArchitect; approval from the competent authorityShows the proposed use, setbacks and access.
Identity documents; POA or joint consentApplicant and all co-ownersEvery occupant on the 7/12 must be on board.
Farmer status / tenure detailsRevenue records; iORA khedut certificateNeeded where tenure or agriculturist status is relevant.
Self-declaration in the prescribed formatApplicantRequired under the September 2024 circulars for applicants on old-tenure or premium land.
Sector NOCs where applicableGPCB, Fire, Forest, CRZ authority, highway / road authority, IrrigationEach one answers a specific objection before it is raised.

Premium and conversion tax are two different charges

Conversion tax is levied on every NA conversion under Section 67A. It is a per square metre amount notified by the State, and the rate depends on whether the land is in a village or small town or in a city of more than one lakh people, and on whether the use is residential or charitable, industrial, or other.

Premium (also called nazrana) applies only to new-tenure (navi sharat) land — land the State originally granted on restricted conditions. Converting such land, or selling it, needs prior permission and usually a premium calculated as a percentage of the Jantri-based market value. The percentage is set by Government Resolutions and varies with land category, purpose and holding period. In November 2024 the State announced a lower premium for one narrow category of restricted-tenure land on NA conversion; that change does not apply to all new-tenure land.

Do not budget premium from a blog post

Premium rates have changed several times and differ by category. The amount that applies to your survey number must be confirmed from the Collectorate or the iORA assessment. Our Jantri guide explains how the Jantri value used in the calculation is looked up.

Development-plan zoning decides what the NA order can say

The Collector will not permit a use the sanctioned development plan does not allow. Where a development plan or Town Planning (TP) scheme applies, check three things before applying: the land-use zone (agricultural, residential, commercial, industrial), whether a TP scheme will deduct part of the plot for roads or public purposes, and the development controls that apply. The Comprehensive General Development Control Regulations (CGDCR) apply across most of Gujarat; confirm the current edition with your architect.

Zoning also matters if the land was bought under the industrial route. Land bought under Section 89A in Kutch (Section 63AA elsewhere) is tied to a bona fide industrial purpose, and the NA application should match that project.

Why NA files get returned or stall

Most problems trace back to the documents and checks above. The issues we see raised most often are:

  • Unresolved tenure: the land is new tenure and premium permission has not been obtained or applied for alongside the NA request.
  • Pending or disputed mutations: a sale or inheritance entry in Village Form 6 is still uncertified, so the 7/12 does not yet show the applicant correctly.
  • Area mismatch: the 7/12, the DILR sheet and the layout plan show different areas — often after re-survey changed block numbers.
  • Zone conflict: the requested use is not permitted in the development-plan zone.
  • No legal access: the plan relies on a track that is not shown in the village map and has no registered right of way, or on highway frontage without an access permission.
  • Missing NOCs: coastal or creek land without a CRZ position, forest-adjoining land without a forest view, or polluting industry without the GPCB position.
  • Co-owner gaps: one heir or co-occupant on the 7/12 has not signed or given consent.

Kutch-specific objections to expect

Land near the Gulf of Kutch, Kandla Creek, the Chirai creeks, Mundra or Jakhau can fall in the Coastal Regulation Zone; mudflats were classified as CRZ-IA in the Kutch CZMP recommended in 2020. Gauchar (grazing land) encroachment and boundaries with the Little Rann’s Wild Ass Sanctuary or the Kutch Desert Wildlife Sanctuary also draw questions. Raise these yourself in the file rather than waiting for a query.

Deemed NA after three months: the law versus practice

Section 65 contains a proviso that if the Collector does not communicate a decision within three months, permission is deemed granted. The three months run from the acknowledgement (which is to be sent within 7 days) or otherwise from receipt of the application. The Supreme Court discussed this proviso in *State of Gujarat v. Patel Raghav Natha* (1969).

In practice, banks, Sub-Registrars and planning authorities want to see an actual NA order before they lend, register or approve plans, so relying on deemed permission is risky. One practitioner estimate for undisputed files is roughly 45 to 90 days, but every file is different and we cannot promise a timeline.

Unverified claims circulating online

Some websites describe a “2025 amendment” making NA automatic after three months, a “2026 Unified Land Code” with self-certification, or automatic “deemed NA” inside finalised TP schemes. We found no gazette notification or Act number for any of these. Treat them as unconfirmed, and also verify that the three-month proviso still reads the same in the current consolidated Code.

Time limits after buying agricultural land

Some purchases under the tenancy laws come with a deadline to apply for NA. The Gujarat Tenancy and Agricultural Lands Laws (Amendment) Act, 2024, notified on 8 February 2024, amends all three tenancy laws including the Kutch Act and replaces a fixed one-year window (Section 63AC in the 1948 Act and its parallel provisions) with a period the State notifies from time to time. Its commencement date was not confirmed in our research, so check the period that applies to your purchase with the Collectorate.

Once you hold the NA order, keep it with the sanad, conversion-tax receipts and the approved layout — every future buyer and lender will ask for them. If you would rather buy land that is already converted, see NA land in Kutch.

Frequently asked questions

What is બિનખેતી (bin-kheti) permission?

It is the Gujarati name for non-agricultural (NA) permission — the Collector’s order under Section 65 of the Gujarat Land Revenue Code allowing agricultural land to be used for industry, commerce, housing or another non-farm purpose.

Can I apply for NA permission online in Gujarat?

Yes. NA applications, including NA combined with premium for new-tenure land, are filed on the iORA portal (iora.gujarat.gov.in), where documents are uploaded and the file is routed to the departments that report on it.

Do I need Section 65 NA permission inside the Gandhidham or Bhuj development authority areas?

Possibly not. Under Section 117 of the Gujarat Town Planning and Urban Development Act, 1976, development permission granted by a development authority under Section 29(2) removes the need for separate Section 65 permission. Confirm with GDA or BHADA whether your survey number is inside their plan area.

Is NA premium payable on all agricultural land?

No. Premium applies to new-tenure (restricted) land. Old-tenure land pays conversion tax under Section 67A but not premium. The applicable premium percentage must be confirmed with the Collectorate.

Does an industrial unit in a GIDC estate need NA permission?

GIDC estates are planned industrial land allotted on long lease, so a buyer does not run a private NA file for the plot. See our guide to GIDC plots in Kutch for how allotment works.

Is “deemed NA” safe to rely on?

The Code provides for deemed permission if the Collector does not decide within three months, but banks, Sub-Registrars and planning authorities generally expect an actual NA order. Treat deemed permission as a last resort and take legal advice.

Buying or selling land in Kutch?

Tell us what you need. We work with landowners, brokers and industrial buyers across every taluka of Kutch.